Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the jetpack domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/thenvskv/public_html/wp-includes/functions.php on line 6131
Railway line between Rainham and Sittingbourne set to reopen after landslip at Newington - UK Daily: Tech, Science, Business & Lifestyle News Updates


Repairs have been completed to fix a landslide which forced a railway line to close.

The land fell away next to the line at Newington near Sittingbourne on February 23 following days of heavy rainfall leading to a 40 metre-long crack along the trackbed.

Trains between Rainham and Faversham were unable to run due to a landslide emerging. Picture: Network Rail

The six-mile stretch between Rainham and Sittingbourne has been out of action since to allow Network Rail engineers to stabilise the slippage and rebuild the embankment.

Network Rail’s geotechnical and structures experts discovered land slipped about five metres down, prompting the closure.

Test trains will be running today after work was completed on Saturday afternoon and the line is expected to reopen to passengers tomorrow morning.

Rail replacement buses have been running in place of trains on the key route from Thanet all the way along the north Kent line connecting the county with London.

In the past week the embankment has been regraded, which involves the excavation of the slipped material before creating a new structure.

Engineers at the scene of the landslip in Newington at the weekend. Picture: Southeastern
The scene of the slippage at Newington . Picture: Southeastern
Work to rebuild the embankment in Newington has been completed. Photo: Network Rail
Work to rebuild the embankment in Newington has been completed. Photo: Network Rail

Steps were cut into the slope before it got backfilled with 3,000 tonnes of stone to help reduce the gradient and strengthen the embankment.

Noise and vibration sensors were also installed so Network Rail could monitor and reduce disruption to residents living nearby.

During the closure, a limited bus service replaced Southeastern trains between Sittingbourne, Newington, Rainham and Gillingham.

An amended train service operated between London Victoria and Gillingham, via Denmark Hill; London St Pancras and Rochester; Sittingbourne and Dover Priory, and Sittingbourne and Ramsgate.