Key Aspects:
- The corrective report for Carnival Breeze‘s recent 86-point CDC sanitation inspection has been submitted.
- Most issues were corrected immediately, though some require parts and maintenance that are now planned.
- Ultraviolet disinfection will not be added to the thalassotherapy pool, though that update may be made in the future.
It can be jarring when a cruise ship comes just one point from failing a health inspection from the US Centers for Disease Control and Prevention (CDC) Vessel Sanitation Program. Carnival Breeze did just that for her inspection on May 14, 2026, but guests do not need to worry.
Carnival Cruise Line has now submitted its “Corrective Action and Follow Up Report” for the inspection. Cruise Hive previously reported on the near-failing score of 86, just one point higher than a failure for the 128,052-gross-ton ship.
Now, 30 of the 36 noted infractions that lowered Carnival Breeze‘s score from her previous perfect 100 in January 2026 have been addressed.
Many of the items were corrected at the time of the inspection. For example, rice stored with incorrect time labels was immediately discarded. Crew members were also retrained on proper labeling and time-control requirements for proper food safety.
Similarly, immediate recleaning of inspected areas that were not within proper sanitary standards corrected a number of inspection problems, along with crew retraining and reviewing of proper procedures to prevent recurrence.
Pest control measures, drying of excessively wet areas, regrouting deck tiles, and reinforcement of supervisory procedures have also helped address different issues.
In many cases, Carnival Breeze crew members went above and beyond to ensure sanitation compliance. A single dirty martini glass found in the Casino Bar, for example, was not only “immediately removed and rewashed, cleaned, and sanitized” but the entire rack of glasses was re-inspected to ensure full compliance with health code guidelines.
What Has Not Been Corrected?
There are some issues noted in the inspection that have not yet been corrected, but not because of a lack of effort.
A pot washing machine in the crew galley was not in working order, and instead, a three-compartment sink is being used for proper cleaning. To correct this, spare parts have been ordered and are awaiting delivery for the issue to be fully resolved.
Spare parts are also on order to correct some condensation issues for dishwashers for the Lido Marketplace, though equipment efficiency has been adjusted as much as possible until the parts arrive.


One specific issue will take longer to correct, as it requires full bulkhead replacement. At the Tides Bar on Deck 10, excessive corrosion on the bulkhead through the bar makes cleaning to exacting standards very difficult.
To mitigate this problem, a “repair and refurbishment plan has been initiated” that includes temporary cleaning to maintain sanitation in the area. To fully correct the problem, “the technical team will address the corrosion through scheduled maintenance and replacement of the bulkhead.”
There is no exact timeline for that work to be completed, but progress will be checked to ensure the bulkhead replacement happens in an appropriate timeframe.
One Issue Will Not Be Fixed
Only one inspection issue aboard Carnival Breeze will not be corrected. The CDC inspectors noted that the thalasso pool on Deck 12 uses gooseneck fountains to recirculate the water, making it an “interactive recreational water facility.”
Because of this, secondary ultraviolet (UV) disinfection is recommended as the best public health practice.
Carnival Breeze was built in 2011-2012. At that time, the most recent Vessel Sanitation Program practices did not yet recommend UV light. Therefore, the ship is still aligned with the best program recommendations according to its construction date.
It is possible that when the ship undergoes her next dry dock, the thalassotherapy pool may be updated to the newest standards. The ship is scheduled for dry dock in late February 2027, but Carnival Cruise Line has not announced what updates or renovations may be part of the maintenance schedule.